The figure on a vendor’s proposal is a fraction of what an ERP system costs. Software fees are visible. Implementation services are estimated. Your own people’s time, the integrations, the data work, the training and the years of running the system afterward are often left out entirely. Total cost of ownership puts all of it on one page, over a period long enough to reflect how long you will actually keep the system.
Further reading: books on IT business cases and cost management (Amazon). We may earn a commission if you buy through this link.
Choose the period
Organizations typically keep an ERP for ten years or more. Compare vendors over at least five years, and preferably seven to ten. A short horizon favors options that are cheap to start and expensive to run.
What to count
| Category | Includes | Often missed |
|---|---|---|
| Software | Subscription, or license plus annual maintenance | Price increases at renewal, extra modules, test environments, storage and transaction overages |
| Implementation services | Partner fees for design, configuration, testing, cutover | Change orders, travel, post-go-live support |
| Internal staff | Project team time, backfill for people seconded to the project | Usually the largest hidden cost |
| Data | Cleansing, conversion, validation | Several rounds of trial conversions |
| Integration | Building and testing interfaces, integration platform fees | Ongoing maintenance of each interface |
| Reporting | Rebuilding reports, analytics tools, data warehouse | Almost always underestimated |
| Change and training | Communications, training development and delivery | Productivity dip after go-live |
| Infrastructure | For on-premises: servers, databases, hosting, disaster recovery | Hardware refresh partway through |
| Running the system | Support team, administrators, vendor support, managed services | Testing every release |
| Third-party products | Tax engines, document capture, e-signature, planning tools | Each has its own renewal |
| Old system | Running in parallel, archiving, decommissioning | Keeping read-only access for audits |
Cloud and on-premises look different
- Cloud subscription: lower cost at the start, steady annual fees that usually rise, infrastructure and upgrades included, little hardware.
- On-premises license: large upfront purchase, annual maintenance, your own servers and staff, periodic upgrade projects.
Over ten years the totals can be closer than the first-year figures suggest. Model both honestly, including upgrade projects for on-premises and price escalation for subscriptions.
Building the model
- Use one spreadsheet with a column for each year and a row for each cost line.
- Give every vendor the same pricing template, with the same users, modules and volumes. See the RFP guide.
- Add your own estimates for internal time and the items vendors do not quote.
- State assumptions beside each number: user growth, annual increase, staff rates.
- Add a contingency. Fifteen to twenty-five percent on implementation is common, and experienced project managers rarely regret it.
- Test the result: what if the project runs six months long, or users double?
Questions that change the numbers
- How is the subscription measured, and what happens when you exceed it? See licensing metrics explained.
- What is the cap on increases at renewal? See the SaaS renewal guide.
- Is the implementation quote fixed price or time and materials, and what does it assume you will do?
- Which requirements need third-party products?
- How many environments are included?
- What does it cost to get your data out at the end?
Cost is half of the case
A total cost figure means little without the benefits beside it. Estimate those as carefully: time saved, inventory reduced, systems retired, errors avoided. Then the comparison is value, not just price. See how ERP improves business performance.
Common mistakes
- Comparing first-year cost only.
- Leaving out internal staff time.
- Accepting each vendor’s own pricing format.
- Assuming no change orders.
- Ignoring the cost of customizations at every future upgrade.
Frequently asked questions
How much do services cost relative to software?
It varies widely with scope and complexity. Implementation services commonly equal or exceed the first years of software fees, which is why they deserve as much scrutiny.
Who should own the model?
Finance, with input from IT and the project lead, and reviewed by the sponsor.
How often should it be updated?
At each major decision point, and whenever scope changes.