ERP projects involve more people, from more departments, than almost any other project an organisation runs. When it is unclear who decides, who does the work and who merely needs to be told, tasks are either done twice or not at all. A RACI matrix is a simple way to make those responsibilities explicit. This guide explains RACI, shows a sample matrix for an ERP implementation, and gives practical rules for building your own.
What RACI means
- Responsible (R): the person or people who do the work.
- Accountable (A): the one person who answers for the result and signs it off. There is only ever one A for each activity.
- Consulted (C): people whose input is needed before the work is finished. Communication is two-way.
- Informed (I): people who are told the outcome. Communication is one-way.
The roles on an ERP project
The roles below appear on most ERP projects. Smaller organisations combine several in one person. A full description of each is in the best team structure for ERP implementations.
- Executive sponsor: the senior executive who owns the business case and has final authority.
- Steering committee: senior managers who approve scope, budget and major decisions. See the ERP steering committee.
- Project manager: plans and runs the project day to day.
- Business process owners: managers who own each end-to-end process and decide how it will work.
- Functional leads and key users: experienced staff who design, configure with the consultants, test and train.
- IT or technical lead: responsible for integrations, data migration tooling, security and environments.
- Implementation partner: the vendor’s or partner’s consultants who bring product knowledge and method.
- Change and training lead: plans communication, training and readiness.
- End users: everyone who will use the system.
Sample ERP implementation RACI matrix
Use this as a starting point and adjust it to your organisation.
| Activity | Sponsor | Steering | PM | Process owners | Key users | IT lead | Partner |
|---|---|---|---|---|---|---|---|
| Business case and objectives | A | C | R | C | I | C | I |
| Scope definition and changes | C | A | R | C | I | C | C |
| Project plan and budget tracking | I | A | R | I | I | C | C |
| Process design decisions | I | I | C | A | R | C | R |
| System configuration | I | I | C | C | R | C | A |
| Customisation approval | C | A | R | C | I | C | C |
| Data cleansing | I | I | C | A | R | C | C |
| Data migration loads | I | I | C | C | C | A | R |
| Integrations | I | I | C | C | C | A | R |
| Security roles and access | I | I | C | A | C | R | C |
| User acceptance testing | I | I | C | A | R | C | C |
| Training delivery | I | I | A | C | R | I | C |
| Cutover plan | I | C | A | C | R | R | R |
| Go or no-go decision | A | R | C | C | I | C | C |
| Support after go-live | I | I | A | C | R | R | R |
How to build your own RACI in five steps
- List the activities and decisions. Work at the level of deliverables and decisions, around 15 to 30 rows. A matrix with hundreds of tasks will not be read.
- List the roles, not the names. Roles outlast individual people. Keep a separate list that maps people to roles.
- Fill in the R and A first. Every row needs at least one R and exactly one A.
- Add C and I sparingly. Each C is someone the team must wait for. Each I is a message someone must send.
- Review it with the people named. A matrix nobody has agreed to is only a wish. Have the steering committee approve it and revisit it at each project phase.
Common mistakes
- More than one A. Shared accountability means nobody is accountable. Pick one.
- The partner is accountable for business decisions. Consultants can be responsible for configuration, but the organisation must own its process design, data and acceptance.
- The project manager is A for everything. That hides the fact that process owners have decisions to make.
- Too many people consulted. Design slows to the pace of the busiest diary.
- Data has no owner. Data cleansing is business work. If it is assigned to IT, it will not be done properly.
- The matrix is filed and forgotten. Refer to it when a dispute or a gap appears. That is when it earns its keep.
Unclear ownership sits behind several of the causes listed in why ERP implementations fail.
Responsibilities after go-live
The project RACI ends at hand-over. Running the system needs its own allocation of duties covering incidents, changes, updates, security and reporting. See ERP support team structure.
Frequently asked questions
What is the difference between responsible and accountable?
The responsible person does the work. The accountable person answers for it and approves it. On small tasks one person can be both.
Who is accountable for an ERP implementation overall?
The executive sponsor. The project manager is responsible for delivering the plan, but the sponsor owns the business case and the result.
Is RACI the only option?
No. Variants such as RASCI add a Support role, and some organisations use DACI for decisions. RACI is the most widely understood and is enough for most ERP projects.
Summary
A one-page RACI agreed at the start prevents weeks of confusion later. Keep it short, give every activity one accountable owner, make sure the business owns its decisions and its data, and update it as the project moves from design to testing to go-live.